Build your team's RACI

By High Performing Teams · 5 min read

Illustration of a team around a long table filling in a large paper grid with marker pens

Introduction

Build your team's RACI is a 60-minute session in which your team lists its main tasks and decisions, then agrees who is Responsible, Accountable, Consulted, and Informed for each one. Anyone in the team can run it. Follow the six steps below, each with a tip for whoever is facilitating, and fill in the free template as you go.

At a glance

  • Time: 60 minutes
  • Recommended team size: three to 12
  • Larger teams: allow an extra 30 minutes, and work in smaller groups for the discussion steps
  • You need: a whiteboard or shared screen, sticky notes, and the template
  • You leave with: a RACI grid the whole team agreed, and a date to check it

Before you start

Choose someone to facilitate. It is a light role: they keep time, move the group through the steps, and make sure everyone is heard. No training is needed, and each step below includes a facilitator tip. It works best if the facilitator is not the team leader, so the leader can take part as an equal.

Ask everyone to come with two or three tasks or decisions where it has not been clear who owns them. These are where the session pays back most.

Step 1 What do we need to own? 10 minutes

  1. Ask each person to write the team's main tasks and decisions on sticky notes, one per note
  2. Put them up and group duplicates
  3. Agree the eight to 12 that matter most, and write them down the side of the grid
Facilitator tip: decisions cause more confusion than tasks. Make sure the list includes things like 'approve spending' as well as 'do the work'.

Step 2 Who is involved? 5 minutes

  1. Write each team member's name across the top of the grid
  2. Add anyone outside the team who regularly needs to be consulted or informed, such as another team or a manager
Facilitator tip: use names, not job titles. 'Marketing' cannot be accountable; a person can.

Step 3 Who is accountable? 15 minutes

  1. Go through each task and agree the one person who owns the result
  2. Write an A in their column
  3. If the team cannot agree, note it and move on; come back to it in step 6
Facilitator tip: this is the step that matters most, so give it the most time. If two people both claim the A, ask 'who would answer for it if it went wrong?'

Step 4 Who does the work? 10 minutes

  1. For each task, mark an R for whoever does the work
  2. The accountable person can also be responsible; write both letters if so
  3. Make sure every task has at least one R
Facilitator tip: watch for tasks where everyone is an R. That often means nobody is really doing it.

Step 5 Who needs to know? 10 minutes

  1. Mark a C for anyone whose input is needed before the work is done
  2. Mark an I for anyone who just needs to be told afterwards
  3. Challenge every C: does their input really change the outcome?
Facilitator tip: most teams consult too many people. Moving a C to an I is one of the quickest ways to speed a team up.

Step 6 Does it work? 10 minutes

  1. Check every task has exactly one A and at least one R
  2. Read across each person's row: is anyone overloaded, or left out?
  3. Return to any task the team could not agree on, and settle it
  4. Agree a date to review the grid, ideally in three months
Facilitator tip: read the finished grid aloud and ask each person whether they can commit to their row. Silence in a group is not agreement.

The RACI template

Free download · PDF

RACI template

It is one printable page with space for 10 tasks and eight people, the rules that make RACI work, plus a worked example on the second page. No sign-up needed.

Download PDF

An example RACI

Worked example

Here is a RACI built in this session by a six-person events team at a charity, planning its annual fundraising dinner. Use it to see how a team uses the grid, not as a script.

01 What we listed

Ten tasks and decisions, from setting the budget and booking the venue to approving the guest list and thanking sponsors afterwards.

02 Where accountability was unclear

Two people both thought they owned the sponsor list. We agreed the head of partnerships is accountable, and the events coordinator is responsible for the day-to-day contact.

03 Where we consulted too many people

Five people were consulted on the menu. We cut it to two, and moved the rest to informed.

04 Who was overloaded

The team leader had six As out of 10. We moved two, the venue and the running order, to the events coordinator.

05 Our review

We check the grid a month before the dinner, and again afterwards, ready for next year. The team leader brings it back.

After the session

Share the finished grid within a day, and put it somewhere the team will see it. When a question comes up about who owns something, check the grid first. Update it whenever someone joins or leaves, or the work changes.

Want the thinking behind the grid? Read what is a RACI matrix?

Running it with a larger team

With more than 12 people, allow about 90 minutes. In steps 3 and 4, split into small groups of four to six, each taking a share of the tasks, then bring the grid back together and check it as a whole team in step 6. With just two or three people, the same steps take 30 to 40 minutes.

Running it remotely

The session works just as well online. Use a shared spreadsheet or whiteboard for the grid, and allow an extra 10 minutes for the technology.

Using AI

An AI tool can give you a head start. Before the session, give it your list of tasks and the team's names, and ask for a first draft of the grid. After the session, ask it to check the finished grid against the rules: one A for every task, at least one R, and nobody with too many As.

Treat any draft as a starting point. The value of the session is the team agreeing who owns what, so do not skip steps 3 and 4 because a tool has filled in the grid. If AI will do part of a task, a person is still marked R for checking its work.

Questions people ask

How many tasks should a RACI have?

Start with eight to 12. A grid with 50 rows is rarely used. Cover the tasks and decisions that cause most confusion, and add more only if you need them.

What if two people both want to be accountable?

Ask who would answer for it if it went wrong. If that still does not settle it, split the task into two parts with one owner each.

Should the team leader be accountable for everything?

No. A leader who owns every task becomes a bottleneck. Give accountability to the people closest to the work wherever you can.

Is there a free RACI template?

Yes. Our free RACI template is a one-page PDF with space for 10 tasks and eight people, plus a worked example.

Can AI build a RACI for us?

It can draft one from a list of tasks, and check a finished grid for missing or doubled As. The team still needs to agree it, or nobody will feel they own their row.